Beamline Startup: High Throughput Hardware
Task list and duration
A rough guide to the required actions and their durations can be found below.
Task Name |
Duration (hrs) |
---|---|
Remove previous installation |
3 |
Install HiTp Frame |
3 |
Install Laser Range Finder |
1 |
Align Beam |
1 |
Shift Detector forward |
1 |
Install I0 stage |
1 |
Network relevant devices |
1 |
To accomodate these tasks, 1-2 days of FACI time is ideal.